Project: Natural Resource Management

Outcome indicator: 1 Test milestone indicator

Description

Test

Progress

66%


Current progress description

Responsibilities

Responsible


Plan

Deadline 18.07.2019
Upcoming measurement date No date set
Measurement interval

Source of Verification

Progress details

Indicator type: Milestone indicator

Milestone progress
Progress description
Target date
Achieved
0%
Baseline
18.07.2019
18.07.2019
33%
Milestone 1
18.07.2019
18.07.2019
66%
Milestone 2
23.07.2019
24.07.2019
100%
Target
18.07.2019
Not completed, yet


Risks and assumptions

Description of risks (and assumptions)


Need for action? Unsure


Action to be taken


Supporting Documents

No documents attached, yet

Notes

-