Project: Natural Resource Management
Objective indicator: 1 Country policy
Current progress description
Dialogue has started between key stakeholders, Minister Green is very interested in supporting the pilot projects. Has has made staff and funds available.
Responsibilities
Responsible | Jack Jackson |
---|
Plan
Deadline | 31/12/2022 |
---|---|
Upcoming measurement date | 31/08/2019 |
Measurement interval | annual |
Source of Verification
Public announcment of government
Progress details
Indicator type: Milestone indicator
Milestone progress
Progress description
Target date
Achieved
No law exists
01/08/2019
01/08/2019
Institutional dialogue
31/10/2019
22/08/2019
Draft available
31/08/2020
13/09/2019
Law adopted
31/08/2022
07/11/2019
Law implemented
31/12/2022
13/01/2021
Risks and assumptions
Description of risks (and assumptions)
We are not sure if our partners will remain as supportive as they are now.
Need for action? Yes